Increased labour and material costs have caused Alexandrina Council’s contentious Goolwa Wharf Precinct Revitalisation Project to blow-out by almost $3 million.
Council was originally set to negotiate and sign a contract with the preferred supplier within the overall $14.5 million project budget following a decision in January, but due to escalating material and labour costs, the amount exceede...